Hanoi City, Securing Accommodating Facilities through 2018-2030

2018-11-20     NGUYEN ANH DUONG 기자

Hanoi, November 20 (Engineering Daily) -- Hanoi People's Committee has submitted the plan to secure accommodating facilities during 2018-2030 to the Ministry of Construction and the Ministry of Transport.

The projects are to be operated between 2018-2025 and 2025-2030.

During the first period, 2018-2025 five facilities projects are proceeded: bus station, truck terminal, logistics center, public car parks, and passenger car terminals. The sum of the projects amount to USD156million and the area occupies 321.51ha..

During the second period, 2025 to 2030, three projects are to be constructed: passenger car terminals, truck terminals, and logistics center.  The sum of the projects amount to USD413million and the area occupies 189ha..

Meanwhile, the truck terminal and passenger car terminal projects in the second period are to be constructed in satellite towns.